Road Sweeping: Due to Tropical Storm Henri, equipment issues, and an ill employee, sweeping on Hanover Road and Brooklyn Turnpike has been delayed. It should begin by Monday, 8/30. We are still planning to deliver stone to those who signed up. Because of the storm, some debris (sticks and leaves) may be present.
Kemp Road: The subsurface work on Kemp Road has been completed. We are awaiting bids from paving contractors. This is a very busy time of year for them, and the rainy weather has slowed them down. We will get the road paved as soon as possible. Meantime, please observe the caution signs and cones that are in place.